Oman e-invoicing go-live planner for Fawtara 2027

Test your supplies. Get your date under Decision 189/2026. Get 39 dated tasks and milestones you can export to Excel or PDF.

  • ✓ Your Fawtara date: test annual supplies against OMR 5M to get 1 Apr or 1 Oct 2027
  • ✓ Ten milestones, 39 tasks: dated backward from go-live so you see what runs in parallel
  • ✓ Plan in your browser. We only see the details you enter to download.
Step 1

Find your Oman e-invoicing go-live date

Enter your annual taxable supplies or pick your band. The plan below moves to your date.

OMR

The Decision tests annual taxable supplies against OMR 5 million. Confirm how your supplies are measured with the Tax Authority.

Defaults to today. Milestones before this date turn red.

Your go-live date
1 April 2027
Above OMR 5 million · Decision 189/2026
Runway
-months
Behind today
-of 10 milestones

Step 2

Work back from 1 Apr 2027

0% · 0 of 39 tasks
Done
Task
Team
Start
End
Month 9 before go-live· Team formed, owner named, systems inventoriedJul 20260/4 done
Programme1 Jul 2026to31 Jul 2026
Programme
1 Jul 2026
31 Jul 2026
Programme1 Jul 2026to31 Jul 2026
Programme
1 Jul 2026
31 Jul 2026
IT1 Jul 2026to31 Jul 2026
IT
1 Jul 2026
31 Jul 2026
Finance1 Jul 2026to31 Jul 2026
Finance
1 Jul 2026
31 Jul 2026
Month 8 before go-live· Gap assessment done: ERP, data, processesAug 20260/4 done
IT1 Aug 2026to31 Aug 2026
IT
1 Aug 2026
31 Aug 2026
Finance1 Aug 2026to31 Aug 2026
Finance
1 Aug 2026
31 Aug 2026
Tax1 Aug 2026to31 Aug 2026
Tax
1 Aug 2026
31 Aug 2026
Tax1 Aug 2026to31 Aug 2026
Tax
1 Aug 2026
31 Aug 2026
Month 7 before go-live· Service provider chosen and contractedSep 20260/4 done
Programme1 Sep 2026to30 Sep 2026
Programme
1 Sep 2026
30 Sep 2026
Programme1 Sep 2026to30 Sep 2026
Programme
1 Sep 2026
30 Sep 2026
IT1 Sep 2026to30 Sep 2026
IT
1 Sep 2026
30 Sep 2026
Programme1 Sep 2026to30 Sep 2026
Programme
1 Sep 2026
30 Sep 2026
Month 6 before go-live· Master data clean-up under way; field mapping startedOct 20260/4 done
Finance1 Oct 2026to31 Oct 2026
Finance
1 Oct 2026
31 Oct 2026
Finance1 Oct 2026to31 Oct 2026
Finance
1 Oct 2026
31 Oct 2026
Finance1 Oct 2026to31 Oct 2026
Finance
1 Oct 2026
31 Oct 2026
IT1 Oct 2026to31 Oct 2026
IT
1 Oct 2026
31 Oct 2026
Month 5 before go-live· Field mapping complete; build startsNov 20260/4 done
Tax1 Nov 2026to30 Nov 2026
Tax
1 Nov 2026
30 Nov 2026
IT1 Nov 2026to30 Nov 2026
IT
1 Nov 2026
30 Nov 2026
IT1 Nov 2026to30 Nov 2026
IT
1 Nov 2026
30 Nov 2026
IT1 Nov 2026to30 Nov 2026
IT
1 Nov 2026
30 Nov 2026
Month 4 before go-live· Sandbox connected; first test invoicesDec 20260/3 done
IT1 Dec 2026to31 Dec 2026
IT
1 Dec 2026
31 Dec 2026
IT1 Dec 2026to31 Dec 2026
IT
1 Dec 2026
31 Dec 2026
IT1 Dec 2026to31 Dec 2026
IT
1 Dec 2026
31 Dec 2026
Month 3 before go-live· Full test cycle: all invoice types, errors, credit notesJan 20270/4 done
IT1 Jan 2027to31 Jan 2027
IT
1 Jan 2027
31 Jan 2027
Finance1 Jan 2027to31 Jan 2027
Finance
1 Jan 2027
31 Jan 2027
IT1 Jan 2027to31 Jan 2027
IT
1 Jan 2027
31 Jan 2027
Tax1 Jan 2027to31 Jan 2027
Tax
1 Jan 2027
31 Jan 2027
Month 2 before go-live· Volume and recovery testing; users trainedFeb 20270/4 done
IT1 Feb 2027to28 Feb 2027
IT
1 Feb 2027
28 Feb 2027
IT1 Feb 2027to28 Feb 2027
IT
1 Feb 2027
28 Feb 2027
Finance1 Feb 2027to28 Feb 2027
Finance
1 Feb 2027
28 Feb 2027
Tax1 Feb 2027to28 Feb 2027
Tax
1 Feb 2027
28 Feb 2027
Month 1 before go-live· Cut-over plan signed off; production set upMar 20270/4 done
Programme1 Mar 2027to31 Mar 2027
Programme
1 Mar 2027
31 Mar 2027
IT1 Mar 2027to31 Mar 2027
IT
1 Mar 2027
31 Mar 2027
IT1 Mar 2027to31 Mar 2027
IT
1 Mar 2027
31 Mar 2027
IT1 Mar 2027to31 Mar 2027
IT
1 Mar 2027
31 Mar 2027
Go-live month· Go-live and hypercareApr 20270/4 done
Programme1 Apr 2027to30 Apr 2027
Programme
1 Apr 2027
30 Apr 2027
Programme1 Apr 2027to30 Apr 2027
Programme
1 Apr 2027
30 Apr 2027
Finance1 Apr 2027to30 Apr 2027
Finance
1 Apr 2027
30 Apr 2027
Programme1 Apr 2027to30 Apr 2027
Programme
1 Apr 2027
30 Apr 2027

Go-live 1 April 2027. Each milestone runs for one calendar month and ends on its last day.

Sources: Oman Tax Authority Decision No. 189/2026, amending the Executive Regulations of the VAT Law (August 2026); Oman Tax Authority e-invoicing FAQ (tms.taxoman.gov.om); PINT OM Billing, Self-Billing and Tax Data Document v1.0.1 release notes, docs.peppol.eu. This planner is general guidance, not tax advice.

How it works

Three steps from threshold to go-live

1

Test your supplies

Enter your annual taxable supplies or pick a band. Above OMR 5 million: 1 April 2027. OMR 5 million or less: 1 October 2027.

2

Set when you start

Work backward from go-live. Red tasks are already behind your start date. Run those in parallel.

3

Track completion

Tick off tasks as teams finish them. Export to Excel or PDF for your steering committee.

The guide

What Decision 189/2026 asks of you

The OMR 5 million rule

Decision 189/2026 tests annual taxable supplies against OMR 5 million. Above OMR 5 million, you go live on 1 April 2027. At OMR 5 million or less, you go live on 1 October 2027, so a business at exactly OMR 5 million is in the October group. Confirm how your supplies are measured with the Tax Authority. Read: Who must comply with Oman e-invoicing, and when

Why the four-phase plan vanished

The Tax Authority published a phased approach first. Decision 189/2026 replaced it entirely with the two dates above. Older guides still mention phases. Confirm your date against the Decision and the Tax Authority's FAQ, not cached articles. Read: Oman e-invoicing timeline

PINT OM and your build schedule

Oman e-invoices are UBL 2.1 XML (PINT OM v1.0.1). The format covers invoices, credit notes and self-billing. PDFs don't count. Mapping your ERP fields to PINT OM is the longest workstream: field mapping, build, sandbox and test take five months of the nine-month plan. Read: Oman e-invoicing formats: PINT OM, UBL 2.1 and XML

Why the plan is nine months long

Nine months lets you run tasks in sequence: team formation, gap assessment, provider selection, data clean-up, UBL build, sandbox testing, full test cycle, volume test, training, cut-over. Shorten the runway and tasks overlap. The planner shows which milestones are already behind on day one. Read: Oman Fawtara e-invoicing: what businesses need to know

FAQ

Oman e-invoicing FAQs

When does e-invoicing become mandatory in Oman?

Decision No. 189/2026 sets two dates. Businesses with taxable supplies above OMR 5 million go live on 1 April 2027. Every other VAT-registered business goes live on 1 October 2027.

How do I know whether I am above OMR 5 million?

The Decision tests annual taxable supplies against OMR 5 million. Above OMR 5 million, you go live on 1 April 2027. At OMR 5 million or less, you go live on 1 October 2027. Confirm how your supplies are measured with the Tax Authority.

What happened to the earlier four-phase timeline?

Decision 189/2026 replaced it. The rollout is now the two dates above. Articles and vendor pages from before August 2026 may still show the old phases.

What format do Oman e-invoices use?

UBL 2.1 XML under PINT OM, the Omani Peppol International Invoice profile. Version 1.0.1 defines Billing for invoices and credit notes, Self-Billing, and the Tax Data Document that reports to the Tax Authority. A PDF can travel with the invoice, but it is not the e-invoice.

Do I need an accredited service provider?

Yes. Fawtara exchanges invoices through service providers accredited by the Tax Authority, and they relay the tax reporting too. Accreditation is under way now. Choosing and contracting a provider sits at month seven in the plan, before data clean-up and build start. Complyance is an approved Fawtara service provider.

Can we go live before our date?

Yes. About 100 companies started using Fawtara voluntarily in a pilot from August 2026, and early adoption is open to other businesses too. Pilot companies are encouraged to go live before their mandatory date. Your service provider can tell you how early onboarding works.

Does the planner store or send my data?

Your annual supplies, start date and ticks stay in this browser's local storage, so the plan is there when you come back. Nothing is sent while you plan. When you download the plan as Excel or PDF, the details you enter in the download form go to Complyance with a short summary of your plan (go-live date, supplies band and progress), so our Oman team can follow up. Clearing site data resets the planner.

Is this tax advice?

No. We built the planner from the published Decision and the Tax Authority's guidance. Confirm your threshold position and go-live date with your tax adviser or the Tax Authority.

Related free tools

Get the data right before you go live

Get e-invoicing right the first time

Connect your ERP once. We validate against PINT OM, deliver over Peppol and report to the Tax Authority, in Oman and across the GCC.

Complyance Logo

One API for Global E-invoicing